Timeline

Calendar/Timeline of Projects

Calendar/Timeline of Projects


As with any project, there is a timeline for the projects’ beginning and completion. These projects are no different. Planning, design, and construction will be ongoing between now and fall 2016. Below is the tentative timeline for all of the buildings affected by the referendum. Note that these dates are subject to change.

Diesel Expansion

Planning and design through April 2013
Bidding June 2013
Construction July 2013-January 2014

Parking Ramp

Planning and design through April 2013
Bidding June 2013
Construction July 2013-January 2014

Urban Agriculture Center

Planning and Design through May 2013
Bidding August 2013
Construction September 2013-April 2014

Integrated Technology Center

Planning and design through July 2013
Bidding April 2014
Construction June 2014-September 2015

Kumm Center (second and fourth floors)

Planning and design through December 2013
Bidding April 2014
Construction July-October 2014

Coleman Center (north half of building)

Planning and design through April 2014
Bidding April 2014
Construction May-December 2014

Coleman Center (south half of building)

Planning and design through April 2014
Bidding April 2014
Construction May-December 2015

Coleman Center (southeast entrance)

Planning and design through February 2016
Bidding March 2016
Construction April-October 2016

Kumm Center (third floor)

Planning and design through March 2016
Bidding April 2016
Construction begins June -September 2016